Water Resources
Greene County, OH — Northwest Regional Water Treatment Plant Improvements
Client
Greene County Sanitary Engineering (OH)
Engineer
AECOM
Delivery Method
Progressive Design-Build
Location
Xenia, Ohio
Size
12 MGD
The Northwest Regional Water Treatment Plant Improvements project added membrane softening technology to Greene County, Ohio’s largest water treatment plant to remove magnesium and calcium. Delivered through a progressive design-build approach, the project also included three new gravity sand filters, increasing plant capacity from 10.5 MGD to 12 MGD, with provisions for future expansion to 16 MGD.
A new 20,000-square-foot pre-engineered metal building (PEMB) was constructed to house critical treatment and support systems, including:
- Reverse osmosis membrane softening equipment
- Membrane feed pumps
- Backwash feed pumps
- Membrane cleaning equipment
- Cartridge filtration equipment
- Interconnecting process piping
- Electrical room
- HVAC equipment
- Operations control room
- Restroom facilities
Through collaborative delivery, the project modernized Greene County’s water treatment infrastructure while improving operational reliability, water quality, and long-term capacity for the growing community.