We’ve reached a big milestone at the City of Middletown, Ohio’s Main & Manchester Improvement Project.
Shook is the design-builder, in partnership with Gresham Smith, on this project, which includes the installation of a 5.1-million-gallon, buried storage reservoir to reduce the number of combined sewer overflows into the Great Miami River. Backfill of the project site is complete.
While things are starting to look serene above ground, there’s plenty going on underground — all equipment is in place and being tested. Next up are concrete walks and landscaping. Acceptance testing will begin in November.