April 21, 2025 News
We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
Employee Ski Trips
February 6, 2025News
ACE Mentor Program of Greater Akron-Canton Bowling Fundraiser
January 31, 2025Mission
The Greene County Northwest Regional WTP Project is Nearing Completion!
January 28, 2025News
The Shook Foundation distributes $15k in its fifth grant cycle
January 27, 2025Mission
Distributing Coats and Care Packs to Chicago Homeless
January 23, 2025Mission
Reid Health Connersville Campus Topping-Out Ceremony
January 21, 2025News
Shook Volunteers at Akron-Canton Regional Foodbank
January 15, 2025Mission
Central Region Holiday Party
December 19, 2024News
Midwest Region Holiday Party
December 17, 2024News
Mid-Atlantic Region Holiday Party
December 13, 2024News
Fall 2024 Co-Op Semester In Review
December 12, 2024News
Great Lakes Region Holiday Party
December 11, 2024News