April 21, 2025 News
We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
Nature Sanctuary and Arboretum Community Service
June 26, 2025Mission
Shook awarded 2025 Carolinas AGC Community Impact Award
June 19, 2025Awards
Hattie Larlham Foundation
June 13, 2025Mission
Chris Besecker named a Rising Star of Construction
June 12, 2025Awards
Generation Dayton Day
June 11, 2025Mission
Drink Local Drink Tap Challenge
June 10, 2025Mission
Shook Named One of the Best Employers in North Carolina for 2025
June 9, 2025Awards
Honor Flight Columbus
June 5, 2025Mission
ACE Mentor Program of Cleveland
June 4, 2025Mission
Up 60 spots on ENR Top 400 Contractors
June 3, 2025Awards
Volunteering with Rebuilding Together Dayton
May 17, 2025Mission