April 21, 2025 News
We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
Stop by Booth 701 and Play the Budget Game!
May 13, 2025News
Join us in Booth 701 at the NCWRA Conference
May 9, 2025News
Dayton Regional STEM School's Topping Out Ceremony
May 6, 2025News
Spring 2025 Co-Op Semester in Review
May 5, 2025News
Kent City Schools Career Technical Education Addition Groundbreaking
April 29, 2025News
Exciting progress on NEORSD's Westerly CEHRT project
April 21, 2025News
spending time improving the Great Lakes community
April 18, 2025Mission
Volunteering at Haven of Rest
April 11, 2025Mission
Activities are Picking up on the Ruhlman Family Center Project
April 10, 2025News
Ryan Levesque Named Triangle Business Journal 40 Under 40 Winner
April 8, 2025Awards
The Mid-Atlantic Picnic Was a Hit
April 4, 2025News
Shook Young Professionals Breakout!
March 28, 2025News