We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
WWTP Improvements Siler City, NC
March 27, 2025News
Sponsoring Connect for Success' S.H.E.D. Event
March 26, 2025Mission
Reid Health's New Ambulatory Care Center is Taking Shape
March 25, 2025News
Equipment Center Installs Community Cupboards in Harrison Township
March 21, 2025Mission
Providing Hands-On Construction Experience at The Big Hoopla STEM Challenge
March 20, 2025Mission
Women in Construction: Kelsey Greco-Phelps
March 19, 2025News
Sleep in Heavenly Peace Delivery Event
March 19, 2025Mission
Women in Construction: Melissa Lear
March 18, 2025News
Mid-Atlantic SYP group Equipment Tour
March 18, 2025News
Women in Construction: Leslie Panfil
March 15, 2025News
Women in Construction: Rachel Mulholland
March 13, 2025News
Preble County Industry Sectors Day
March 13, 2025News