April 21, 2025 News
We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
Women in Construction: Everree Springer
March 6, 2025News
Women in Construction: Penny Combs
March 5, 2025News
Women in Construction: Angelica Barraza
March 5, 2025News
Women in Construction: Esme Garcia
March 4, 2025News
Women in Construction: Angel Fortner
March 3, 2025News
Midwest Co-Ops Visit the Dayton Regional STEM School
February 26, 2025News
Wagram Road WWTC Progress Update
February 17, 2025News
Fostering Bright Futures 5k
February 14, 2025Mission
Employee Ski Trips
February 6, 2025News
ACE Mentor Program of Greater Akron-Canton Bowling Fundraiser
January 31, 2025Mission
The Greene County Northwest Regional WTP Project is Nearing Completion!
January 28, 2025News
The Shook Foundation distributes $15k in its fifth grant cycle
January 27, 2025Mission