We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
Volunteering at the Licking River Round Up
September 20, 2024Mission
I Build America - Ohio features Shook's Caleb Arnold
September 19, 2024News
Shook Celebrates Award Wins at 2024 Cogence Alliance Town Hall
September 18, 2024Awards
Project Spotlight: Robin Industries
September 17, 2024News
Shook raises awareness on Suicide Prevention
September 16, 2024News
Shook gives back to dementia community
September 13, 2024Mission
Manchester LSD Celebrates New High School
September 11, 2024News
We hope to see you at the 2024 Cogence Alliance Town Hall
September 10, 2024News
OWEA Buckeye Bulletin features Shook's Global Mission Trip Program
September 9, 2024Mission
Living our Mission: August 2024 Project Outreach
September 5, 2024Mission
Mid-Atlantic Team Outing: RushHour Karting
September 4, 2024News
Third Annual Shook Foundation Invitational - Cleveland
September 3, 2024Mission