April 21, 2025 News
We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
Making School supplies with Crayons To Classrooms
June 24, 2024Mission
Drink Local Drink Tap's 4 Miles 4 Water Run/Walk
June 20, 2024Mission
Salem Regional Medical Center Surgery and Outpatient Pavilion Complete
June 17, 2024News
Completion of Otterbein SeniorLife Renovation
June 13, 2024News
Tippecanoe Middle School Construction Career Day
June 7, 2024News
Top Considerations for Choosing a Project Delivery Method
June 5, 2024Insights
West Carrollton City Schools' New Facilities Are Taking Shape
June 4, 2024News
Shook Releases Documentary About Mission Trip to Thailand
June 3, 2024Mission
Progress Continues on the Neuse River Sidestream Treatment Project
May 31, 2024News
Progress Continues on Manchester Local Schools' Building Projects
May 30, 2024News
Top Notch Standards of Excellence Event
May 24, 2024News
Shook Conducts Safety Trainings Across Various Projects
May 22, 2024News