April 21, 2025 News
We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
Women in Construction: Emma Fisher
March 8, 2024News
Women in Construction: Terri Mention
March 7, 2024News
Women in Construction: Melissa Lear
March 6, 2024News
Women in Construction: Logan Spradlin
March 6, 2024News
Women in Construction: Leah Reitano
March 4, 2024News
Thailand Mission Trip: So Long Thailand
February 29, 2024Mission
Thailand Mission Trip: Mission Complete
February 26, 2024Mission
Thailand Mission Trip: Construction Progress
February 22, 2024Mission
Thailand Mission Trip: The Team Has Arrived!
February 19, 2024Mission
Thailand Mission Trip: Ready for Takeoff!
February 13, 2024Mission
West Carrollton Unveils Major School Projects
January 29, 2024News
Announcing our 2024 Mission Trip Partner
January 22, 2024Mission