April 21, 2025 News
We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
Preparing Lunch at St. Vincent de Paul Society, Dayton
September 28, 2023Mission
OWEA Webinar: NPDES Total Phosphorus Permit Requirements
September 8, 2023News
2nd Annual Shook Foundation Invitational - Cleveland
August 31, 2023Mission
One Water Ohio Technical Conference 2023
August 29, 2023News
2023 Q1 & Q2 Craft Safety Awards
August 28, 2023News
Education Trail Improvement - Wilson, NC
August 22, 2023Mission
CEA Building Excellence Award: Brecksville-Broadview Heights PK-5
August 21, 2023Awards
Montgomery County SMART Project Update
August 18, 2023News
Co-Op Emma Fisher Wins ASCE Student Days Challenge
August 17, 2023News
Manchester Local Schools Athletic Stadium Update
August 16, 2023News
Builders Exchange of Dayton Awards
August 15, 2023Awards
Mid-Atlantic Co-Op Celebration
August 7, 2023News