April 21, 2025 News
We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
Shook Construction undertakes new operating model to grow work
December 12, 2023News
Dayton Metro Library Career Adventures Day
December 6, 2023Mission
Supporting Cleveland State University's Construction Management Program
November 30, 2023News
Congratulations to our Happy Shooksgiving Winner: Nine13sports
November 28, 2023Mission
Shook Wins Auman Award for Excellence in Safety
November 21, 2023Awards
Shook Wins Build Ohio Award for Sierra Nevada Corporation Hangar
November 17, 2023Awards
Happy Shooksgiving! It's time to vote!
November 16, 2023Mission
West Carrollton Schools Phase II Building Project Groundbreaking
November 15, 2023News
OSBA Capital Conference and Tradeshow
November 14, 2023News
Tune into the CEA Podcast Hear from Shook Leadership
November 14, 2023Insights
Introducing Careers in Construction in Princeton, NC
November 6, 2023Mission
Q3 2023 Craft Safety Awards
November 2, 2023News