September 24, 2025 News
Work is moving ahead at full speed at the Wastewater Treatment Plant improvement project in Siler City, NC.
Structural concrete is 60% complete on this $62 million project for which Shook is serving as General Contractor. To date, teams also have:
The work continues. Coming up:
Several municipalities and entities — Siler City, City of Sanford, NC, and TriRiver Water — are collaborating on this transformative project, which will increase water capacity for the growing region. The project is expected to be complete in 2027.
Shook's COO, Joe Mellon, Talks 2024 and Why Dayton is 'Exciting'
March 12, 2024News
Women in Construction: Laura Kobak
March 12, 2024News
Women in Construction: Kelsey Greco
March 11, 2024News
Women in Construction: Penny Combs
March 8, 2024News
Women in Construction: Emma Fisher
March 8, 2024News
Women in Construction: Terri Mention
March 7, 2024News
Women in Construction: Melissa Lear
March 6, 2024News
Women in Construction: Logan Spradlin
March 6, 2024News
Women in Construction: Leah Reitano
March 4, 2024News
Thailand Mission Trip: So Long Thailand
February 29, 2024Mission
Thailand Mission Trip: Mission Complete
February 26, 2024Mission
Thailand Mission Trip: Construction Progress
February 22, 2024Mission