September 24, 2025 News
Work is moving ahead at full speed at the Wastewater Treatment Plant improvement project in Siler City, NC.
Structural concrete is 60% complete on this $62 million project for which Shook is serving as General Contractor. To date, teams also have:
The work continues. Coming up:
Several municipalities and entities — Siler City, City of Sanford, NC, and TriRiver Water — are collaborating on this transformative project, which will increase water capacity for the growing region. The project is expected to be complete in 2027.
100 Acts of Service: 37-49
May 13, 2026Mission
Occupied Renovation: What Steps Owners Need to Know to Keep People Safe and Operations Moving
May 11, 2026Insights
Groundbreaking for Bay Village Facilities Improvement Project
May 7, 2026News
100 Acts of Service: 31-36
May 6, 2026Mission
Progress at the Bedford Heights Wastewater Treatment Plant
May 5, 2026News
100 Acts of Service: 28-30
April 27, 2026Mission
100 Acts of Service: 23-27
April 20, 2026Mission
Celebrating the Opening of the New Parma Heights Library
April 14, 2026News
Work at Elizabethtown Wastewater Treatment Plant Moving Along
April 13, 2026News
100 Acts of Service: 19-22
April 8, 2026Mission
Milestone at Tipp City Schools PK-8 School Project
April 7, 2026News
SNC Hangars Unveiled at Ribbon Cutting Ceremony
April 6, 2026News