April 7, 2026 News
Concrete installation has begun at Tipp City Schools’ new PK-8 School, marking a major milestone for the project! After months of planning and site preparation, construction is in full swing.
Shook is serving as the construction manager for the 218,944-square-foot PK-8 school, which will serve nearly 1,800 students.
Teams recently poured 160 yards of foundational concrete in a section of the school that includes the cafeteria kitchen, mechanical room, and locker rooms. The next phase will include a foundational concrete pour in the three-story academic wing.
In addition, teams have completed:
Crews continue to make progress on underground electrical, and plumbing work and are constructing two staircases.
Stay tuned for updates as Tipp City Schools embarks on a transformative facilities construction program. Shook will also manage a comprehensive renovation to Tippecanoe High School, with work taking place during the summers of 2026 and 2027.
Thank you to our design partner, Garmann Miller, and other industry partners as we work to deliver 21st-century learning environments for the district.
Reid Health's New Ambulatory Care Center is Taking Shape
March 25, 2025News
Equipment Center Installs Community Cupboards in Harrison Township
March 21, 2025Mission
Providing Hands-On Construction Experience at The Big Hoopla STEM Challenge
March 20, 2025Mission
Women in Construction: Kelsey Greco-Phelps
March 19, 2025News
Sleep in Heavenly Peace Delivery Event
March 19, 2025Mission
Women in Construction: Melissa Lear
March 18, 2025News
Mid-Atlantic SYP group Equipment Tour
March 18, 2025News
Women in Construction: Leslie Panfil
March 15, 2025News
Women in Construction: Rachel Mulholland
March 13, 2025News
Preble County Industry Sectors Day
March 13, 2025News
Softball Facility Revitalization for Eastern Wake High School
March 10, 2025Mission
Women in Construction: Lexi Barnett
March 10, 2025News