June 24, 2026 News
The Think Dayton Building at the onMain Innovation District is quickly taking shape just south of downtown Dayton.
The elevator shafts and stairwells are in, and steel framing is now underway, highlighting steady progress on the five-story, 120,000-square-foot building.
The Skanska Shook joint venture is serving as construction manager for the project, which will anchor the first phase of onMain and house the district’s Digital Transformation Center.
Next up for the Think Dayton Building: Placing concrete slabs on decks.
This project is a reflection of collaboration at its best. We’re proud to work alongside Skanska, design partner NBBJ, and our dedicated trade partners.
Together, we’re building more than a structure. We’re creating a space designed to foster innovation, connection, and growth in the Dayton community.
2026 Mission Trip: Thank You, Guatemala
March 25, 2026Mission
Steve Pokwo Named Dayton Business Journal 40 Under 40 Winner
March 24, 2026Awards
Why Early Collaboration Delivers Better Outcomes Than Hard Bid
March 23, 2026Insights
100 Acts of Service: 10-13
March 17, 2026Mission
Nora Loftus Named to Notable Women in Law List
March 16, 2026Awards
2026 Mission Trip: Our Final Days in Guatemala
March 12, 2026Mission
Milestone at Siler City Wastewater Treatment Plant
March 11, 2026News
2026 Mission Trip: A Job Well Done!
March 10, 2026Mission
2026 Mission Trip: Work is Underway!
March 6, 2026Mission
Reid Health – Connersville Ambulatory Care Center
March 6, 2026News
Women in Construction Week: Lauren Brown
March 6, 2026News
Women in Construction Week: Rachel Hamm
March 5, 2026News