July 23, 2024 News
Progress on the Mansfield Water Treatment Plant Improvements project continues! Shook serves as the Construction Manager at Risk and the General Trades Contractor on this $30M renovation, working within the confines of the active 10 MGD plant. All work has been carefully planned and executed to prevent disruption to the City's drinking water.
Phase 1 involved the renovation of eight gravity media filters, half of which were original to 1951, as well as complete replacement of the Plant’s chemical feed systems, electrical feed system, I&C system, and many process piping improvements and replacements. Phase 2 involves the renovation of four Floc/Sed Basins, half of which were original to 1951, and replacement of the three High Service Pumps, along with corresponding electrical, control, and process upgrades. With renovation of the final two filters and High Service Pumps/Distribution improvements underway, and the final pieces of equipment set to arrive in the next several months, the project is pushing toward completion next spring!
The Shook Foundation Distributes $60K in its Sixth Grant Cycle
September 8, 2025Mission
Congratulations Carter Daly Recipient of Harry F. Gaeke Memorial Scholarship
September 4, 2025News
BILA Solar North American Headquarters is a Monumental Awards Finalist
September 2, 2025Awards
2025 Construction Employers Association Building Excellence & Craftsmanship Awards
August 27, 2025Awards
Completion of Kershaw Water Treatment Plant
August 26, 2025News
Fourth Annual Shook Foundation Invitational - Cleveland
August 25, 2025Mission
Summer 2025 Co-Op Semester in Review
August 22, 2025News
2025 Builders Exchange of Dayton Awards
August 21, 2025Awards
West Carrollton Elementary School Ribbon Cutting
August 20, 2025News
Shook Named to the 2025 OSBA Business Honor Roll
August 19, 2025Awards
Chris Shafer Recognized as CFO of the Year
August 18, 2025Awards
Northwest Regional Water Treatment Plant Ribbon Cutting
August 14, 2025News