Miami Valley Hospital SE Addition
The Joint Venture team of Skanska Shook served as Construction Manager of the new $135 million patient tower for Premier Health Partner's Miami Valley Hospital. The 180-bed hospital covers 12 floors, totalling approximately 480,000 SF. In addition to the patient rooms, the building houses three operating rooms and five cath labs. A 40-car parking garage also was incorporated into the building's base.
Completed in November 2010, the project has received its LEED Silver certification. To see the Dayton Business Journal Article on LEED Certification click here.
The team's contract also included performing extensive preconstruction services as well as enabling projects to prepare the site for construction.
|